Part 6: Milestone payments
Updated · 1 min read
Not yet reviewed by a builder or a Costa Rican attorney. General information, not legal or tax advice.
In short
Pay against finished work that someone you trust has checked, not by the calendar. Agree the stages and the share of the price for each in the contract.
A guide to the shares, from US data
We found no Costa Rican figures. US national averages for 2024, as a rough guide only (NAHB, January 2025):
| Stage | Share of construction cost (US, 2024) |
|---|---|
| Site work | 7.6% |
| Foundations | 10.5% |
| Framing | 16.6% |
| Exterior finishes | 13.4% |
| Major systems | 19.2% |
| Interior finishes | 24.1% |
| Final steps | 6.5% |
| Other | 2.1% |
Costs on top of the builder's price
- INS workers' insurance: about 1.17% of the assessed value (Howler, undated) or 1.5% (Coldwell Banker Costa Rica, February 2025). Sources differ.
- 13% VAT on construction materials, and social charges of about 42% on labour (Coldwell Banker Costa Rica, February 2025). Ask whether the builder's price includes them.
Work out the numbers: build cost calculator
Sources
- NAHB, "Cost of constructing a home in 2024" (US national survey). Published January 2025. Checked November 13, 2026.
- Howler, "Three stages to building in Costa Rica". Published undated. Checked November 13, 2026.
- Coldwell Banker Costa Rica, "The real cost to build your dream home in Costa Rica". Published February 2025. Checked November 13, 2026.
What changed
- November 13, 2026First published.
Tools for this guide
Stage 5: Build
Pick your team, get the permits and build, often from abroad.
Every guide in this stageTalk it through
Questions about your situation? A virtual tour with an advisor, no obligation.
Book a virtual tour