Building from abroad · Part 6 of 8

Part 6: Milestone payments

Updated · 1 min read

Not yet reviewed by a builder or a Costa Rican attorney. General information, not legal or tax advice.

In short

Pay against finished work that someone you trust has checked, not by the calendar. Agree the stages and the share of the price for each in the contract.

A guide to the shares, from US data

We found no Costa Rican figures. US national averages for 2024, as a rough guide only (NAHB, January 2025):

StageShare of construction cost (US, 2024)
Site work7.6%
Foundations10.5%
Framing16.6%
Exterior finishes13.4%
Major systems19.2%
Interior finishes24.1%
Final steps6.5%
Other2.1%

Costs on top of the builder's price

Work out the numbers: build cost calculator

Sources

  1. NAHB, "Cost of constructing a home in 2024" (US national survey). Published January 2025. Checked November 13, 2026.
  2. Howler, "Three stages to building in Costa Rica". Published undated. Checked November 13, 2026.
  3. Coldwell Banker Costa Rica, "The real cost to build your dream home in Costa Rica". Published February 2025. Checked November 13, 2026.

What changed

  • November 13, 2026First published.

Email me when these rules change

Checklist

Questions to ask a builder: the questions to ask, on one printable page.

Get the checklist
Stage 5: Build

Pick your team, get the permits and build, often from abroad.

Every guide in this stage
Talk it through

Questions about your situation? A virtual tour with an advisor, no obligation.

Book a virtual tour